Three engagements, start to finish

What we walked into, and what was in place when we left.

  1. Battery storage project, WA: completions rebuilt mid-construction

    Construction completions for contractor Genus

    4 weeks

    to stand up a complete completions system from a standing start

    The principal contractor had been removed from site. The project was behind schedule, over budget, and had no working completions system to hand over from.

    • Stood up a complete completions system in four weeks, from a standing start
    • Built the systemisation, ITR registers and workflows covering 5,000 to 7,000 ITRs
    • Scaled the completions team up to work an aggressive recovery schedule
    • Completed the construction completions scope for contractor Genus
  2. Same project, into commissioning: the CCMS stayed with us

    Retained under a separate contract

    With construction closing out, the client wanted completions data to carry straight into commissioning instead of being rebuilt for a second time.

    • Retained under a separate contract to run the CCMS through commissioning
    • Worked alongside the client’s commissioning contractor rather than in parallel to them
    • Kept one source of truth for completions data from construction into start up
    • Client and contractor are now in discussion with us on further projects
  3. WA processing facility: system built before the field work

    Early works and bridging works

    4 months

    to migrate from MCplus to PIMS and deliver the new scope

    Engaged at early works and bridging works, before the bulk of construction. The completions system could be designed properly rather than retrofitted under pressure.

    • Migrated the project from MCplus to PIMS and delivered the new scope in four months
    • Built the majority of the systemisation and ITR registers up front
    • Completions procedures and execution plan written, approved and in place
    • Field data structured and traceable from the first walkdown

Further detail on any of these engagements is available on request.

Before and after

What changes when completions is run as a system: what goes, and what takes its place.

Before Corefield Systems

  • ITRs scattered across spreadsheets
  • Punch lists no one fully trusts
  • Handover dossier assembled in a panic
  • Reporting that raises more questions than it answers
  • Audit findings late, when they hurt most

After

  • One completions system, field to handover
  • Clean, traceable ITR and QVD data
  • Dossiers that pass acceptance first time
  • Reporting leadership can act on
  • Issues found early, when they’re cheap to fix

What clients say

“Attie and Ruben ran the completions side of the CBESS1 commissioning for us. They kept the PIMS data clean, kept the reporting current, and gave us good visibility into where completions stood throughout commissioning. They also found ways to automate a lot of the reporting and admin that would otherwise have taken the team a significant amount of time. I’d be happy to have them involved in any project I’m running.”
Luis QueirosCommissioning Manager, Future Energy, Synergy
“We brought Corefield in to handle completions on the WBESS project. They set the system up properly, engaged with the project engineering and construction teams where it mattered, kept the ITR and completions data clean through to sign off, jumping through hoops that typically crop up, and gave us reporting we could rely on. For a small team they know the ropes and what completions a construction project requires. I would definitely use them again.”
Don TesterProject Manager, WBESS

Published with each client’s written approval.

Want results like these?

Book a consult. We will review where your completions stand and map the path to a clean handover.

Or email info@corefieldsystems.com. We reply within one business day.

Book a completions consult